Mammoth Hot Springs, WY — National Parks Director (NPS) Chuck Sams and Superintendant for Yellowstone National Park, Cam Sholly, announced Sunday that the park would receive 50 million dollars to restore temporary access to roads damaged from floods. 

The news release says the money will restore roads to Gardiner and Cooke City, Montana. Plans are finalized to provide temporary access to Old Gardiner Road between the park and Gardiner. NPS believes the Old Gardiner Road project will significantly improve over the next few months. The Federal Highway Administration (FHA) is working on a current road project that will be diverted to the Old Gardiner Road project

Along with the Southern Loop Entrance scheduled to re-open on June 22 at 8 am, the Northern Loop entrance is also expected to open in the next two weeks, which is sooner than anticipated. The road will reopen after clean-up efforts, repairs, and an inspection of infrastructure are finished. 

During the summer construction, the FHA and NPS are working together to find options for restoring temporary and permanent access to the northeastern entrance of the park between Silver Gate and Cooke City, Montana. The current road is impassable to traffic between Lamar Vallet and Silver Gate. The timeline and funding for this project have yet to be determined. 

A temporary visitor access plan based on license plate numbers will be used to keep track of visitors in the park. 

#####

Full Press Release below: 

MAMMOTH HOT SPRINGS, Wyo. — During a visit to Yellowstone National Park and Gardiner, Montana, on Sunday, June 19, National Park Service Director Chuck Sams with Yellowstone National Park Superintendent Cam Sholly announced $50 million to kick-start recovery efforts from record breaking floods.

They also announced that in addition to the park’s southern loop reopening on June 22, the park’s northern loop is expected to reopen in two weeks or less following completion of clean-up, repairs and final inspection of the northern loop infrastructure. This will allow visitors to access Dunraven Pass, Tower, Mammoth Hot Springs and Norris opening visitor access to approximately 80 percent of Yellowstone National Park. Additional details on access will be announced in the coming weeks. 

The initial $50 million will be used to restore temporary access to Gardiner and Cooke City, Montana and other additional sites. Plans are being finalized for improving the Old Gardiner Road for temporary access between Yellowstone and Gardiner, Montana. In partnership with the Federal Highway Administration, road construction crews and materials that were already in the park for a previously scheduled road project to repair 22 miles of the Grand Loop Road between Old Faithful and West Thumb Geyser Basin will be diverted to the Old Gardiner Road project.   

The NPS currently anticipates the Old Gardiner Road will be substantially improved over the upcoming months, ensuring that essential emergency services, food, supplies and other administrative needs will be available throughout the winter months. As work proceeds through the summer, the NPS will look for opportunities to restore limited visitor access at the park’s North Entrance. Emergency environmental and historic preservation compliance is underway in accordance with the National Historic Preservation and Environmental Policy Acts. Permanent reconstruction options are being developed and alternatives will be completed in the upcoming months.   

In addition to plans to reopen Yellowstone’s northern loop much sooner than initially anticipated, the NPS is working with the Federal Highway Administration on a range of temporary and permanent options to restore access to Silver Gate and Cooke City at the park’s northeast entrance. Currently, the Northeast Entrance Road is impassible between Lamar Valley and Silver Gate. Cost, funding and timelines are not yet available for these short or long-term repairs to the Northeast Entrance Road but will be released as soon as possible.   

Announced on June 18, Yellowstone will restore access to the southern loop of the park at 8 a.m. Wednesday, June 22, via the East (Cody), West (West Yellowstone), and South (Grand Teton/Jackson) entrances. Accessible areas include Madison, Old Faithful, Grant Village, Lake Village, Canyon Village and Norris. To balance the demand for visitor access, park resource protection and economic interests of the communities, the park will institute an interim visitor access plan based on license plate numbers. To learn more about the alternate license plate entry system, visit Yellowstone’s flood recovery webpage.